Change transition rules

The following information identifies each supported transition in the Change Management workflow for a normal change. Notice that it is possible for a record to return to an earlier phase in the workflow if the status changes to a certain value.

The Action or Condition column in the tables for each phase, show fields that contain data either entered by the end user or automatically provided by Service Management. At the start of each phase, Service Management verifies that the user-defined values set in the last phase are unchanged. If there is a change, the record can return to a prior phase or repeat an action.

All changes begin with the Log phase.

All changes transition from Log to the Evaluate phase.

Changes transition from Evaluate to the Plan or Abandon phase.

Changes transition from Plan to the Approve plan or Abandon phase.

Changes transition from Approve plan to the Build and test, Approve deployment, Plan, or Abandon phase.

Changes transition from Build and test to the Approve deployment or Abandon phase.

Changes transition from Approve deployment to the Execute, Build and test, Plan, or Abandon phase.

Changes transition from Execute to the CMDB Update, Remediate, or Abandon phase.

Changes transition from CMDB update to the Review or Abandon phase.

All changes transition from Review to the Close phase.

All changes transition from Remediate to the Review phase.