Schedule Data Push Jobs

UCMDB allows you to schedule job executions directly from a data push job.

  1. Log on to UCMDB as an administrator.
  2. Navigate to Data Flow Management > Integration Studio.

    UCMDB displays a list of existing integration points.

  3. Select the integration point you created for the APM - UCMDB integration.

  4. Select the APM Push job.

  5. Click the Edit Integration Job button.

    The Edit Integration Job dialog opens.

    Note UCMDB allows you to define two different schedules for two types of data push: Changes Synchronization (or Delta Synchronization) and All Data Synchronization (or Full Synchronization). It is recommended to use the Changes Sync schedule to only synchronize changes and avoid synchronizing the entire set of data each time.

  6. Define a schedule for Changes Synchronization or Delta Synchronization.

    1. Click on the Changes Synchronization tab (or Delta Synchronization).

    2. Select the Scheduler enabled option.

    3. Select the scheduling options you want to use.

  7. Click the All Data Synchronization tab (or Full Synchronization) and select the scheduling options you want to use.

  8. Click OK.
  9. Save the integration point.