Complete a phase

Applies to User Roles:

Change Manager

Change Coordinator

When all the conditions for completing a phase are met, you can close the phase.

To complete a phase, follow these steps:

  1. Click Change Management > Changes > Change Queue.
  2. Click the change request to display its details.
  3. Click Close Phase.