Handle long-running tasks

Applies to User Roles:

System Administrator

Follow the these steps to identify a "long-running" task:

  1. Log in to Service Manager as system administrator.
  2. Click Tailoring > Integration Manager.
  3. Click Log, set the Status field to In Progress, and then click Filter.

If a task remains in the In Progress status for a long time, then this task is a "long-running" task.

Follow these steps to handle a "long-running" task:

  1. Log in to Service Manager as system administrator.
  2. Click Tailoring > Integration Manager.
  3. Select the integration instance to which the "long-running" task belongs, and then click Disable.
  4. Click Miscellaneous > System Status, and then wait until the scheduler for the integration instance disappears.

    Note You need to click the Refresh Display button to see the latest system status.

  5. Go back to Integration Manager, select the corresponding integration instance, and then click Task.
  6. Open the "long-running" task.
  7. Perform one of the following actions according to your needs:

    • Click the Merge button and then manipulate the data in the task.

      This action only applies to the outbound tasks.

    • Select the Expired check box.

      In this way, the task will not be processed.

    • Click the Delete button to delete the task.

      In this way, you may have to ask the integration partner to resend the record. Be careful when you delete a task, this action may results in data loss.