Integrate > HPE Operations Orchestration (OO) > Automated deployment of changes > Update OO flow links in a change record

Update OO flow links in a change record

User roles: Change Manager, Change Coordinator, and Release Manager

Note You can update OO flow links only in a change record of a category other than either of the following:

  • Subscription
  • Unplanned Change

To update OO flow links in a change record:

  1. Log on to the Service Manager Web client. 
  2. Open an existing change record that meets the conditions previously mentioned.
  3. In the OO Flow Links section, click the Seq No of an OO flow link that you want to update. The OO Flow Link Detail form opens.
  4. Update the fields as necessary, and then click Save.
  5. Click Cancel. You are returned to the Change form.
  6. Click Save to save the change record.