Develop > Document Engine Guide > Work order example overview > Test the work order example

Test the work order example

After you complete the tasks to create a work order system, you need to verify that it works correctly. To verify the basic functionality of the work order example, do the following:

  • In Incident Manager, find an open incident or create one.
  • Use the Options menu or button on the tool bar to create a work order. Create Workorder should display on the Options menu.
  • In the Workorder wizard, enter the data to create a work order for the incident.
  • Add the work order to the incident and save the changes to the incident.
  • Open the incident for editing, and from the WorkOrder tab edit the work order.
  • Save your changes.
  • Open the incident again, and this time edit the work order and close it.
  • You should now be able to close the incident.
  • Repeat these steps, but this time create two work orders for an incident.
  • Close only one work order and then attempt to close the incident. The system should generate an error message indicating that there are still open work orders for the incident, and therefore it cannot be closed.
  • Close all work orders for the incident. You should now be able to close the incident.